Skip to content
Get a quote

Foundations for a Single Storey SIPs Extension

A clad SIP wall weighs a small fraction of the brick and block wall it replaces. That lets the foundations for a single storey SIPs extension be narrower and opens the door to screw piles, but it does not make them shallower. Depth is decided by the soil, the trees and the drains. Typical published costs run from £1,000 to £3,000 for strip foundations on firm ground to £NaN and up for piles.

£1,000 to £3,000strip foundations on firm ground, including VAT

Get a quote

What decides the type

  • Soil. Firm, non-shrinking ground takes a simple strip. Clay that swells and shrinks pushes the dig deeper.
  • Trees. A mature oak, willow or poplar within its own height of the extension changes everything on clay.
  • Drains. A sewer under or beside the footprint needs bridging and the water company's consent.
  • Access. If a digger cannot reach the back garden, hand-dug trenches or screw piles come into play.
  • The existing house. New foundations normally go at least as deep as the ones they sit beside.

Foundation types and typical costs

TypeTypical price, including VAT
Concrete strip or trench fillTrenches filled with concrete; the default on good ground£1,000 to £3,000
Reinforced raftOne slab that spreads the load on soft or variable ground£3,000 to £6,000
Piles or screw piles with a ring beamPoor ground, trees close by, or no digger accessPriced by your engineer after a ground investigation; can add several thousand pounds
Structural engineer, single storeyNeeded for rafts and piles, and for any dig near trees on clay£600 to £1,200
Party wall surveyor, per neighbour, one agreed surveyorIf you dig close to a neighbour's building£700 to £1,500

Typical national ranges for 2026, including VAT. London and the South East usually cost 20 to 40% more. A guide, not a quote.

Where these figures come from

Open the cost calculator

Lighter walls, same ground

A 142 mm SIP wall panel weighs roughly 20 to 25 kg per square metre before cladding. A brick outer leaf, a block inner leaf and the plaster come to nearer 400 kg. Add the roof and a single-storey SIPs wall puts a very small line load on its footing.

Approved Document A sets minimum strip widths by soil type and wall load, and a SIPs extension sits at the light end of that table. So the trench can often be narrower than a bricklayer would expect, and you pour less concrete.

Depth is a different question. The same document sets 450 mm as the minimum to stay below frost and asks for more in shrinkable clay, where 750 mm is the usual starting point. Near trees on shrinkable clay the NHBC's published tables, which most building control officers follow, can call for two metres or more. A light building is, if anything, more easily lifted by swelling clay than a heavy one. Do not let anyone tell you SIPs need "hardly any foundations".

Strip and trench fill

The standard answer. A trench 450 to 600 mm wide is dug to the agreed depth, inspected by building control, and filled with concrete either part way (strip, with blockwork up to ground level) or almost to the top (trench fill). A ground-bearing slab or a suspended floor then spans between the walls.

It suits most gardens, any groundworker can build it, and it is the cheapest route on firm soil. It produces a lot of spoil: a 4 m by 6 m extension dug a metre deep fills several skips.

Raft

A reinforced concrete slab, thickened at the edges, that carries the whole extension as one piece. Engineers choose it for made ground, soft clay and sites where strips would need to be impractically deep. An insulated raft, cast inside a tray of structural insulation, gives the floor its U-value at the same time and removes the cold edge where slab meets wall.

A raft is always engineer-designed, and the edge detail has to suit the sole plate, so the SIPs supplier and the engineer need to speak before the steel is ordered.

Screw piles

A compact rig screws steel shafts, each with a helical plate near the tip, down to the resistance the engineer has specified. A steel or timber ring beam sits on the pile heads and carries an insulated timber floor and the panels above.

This is where the low weight of SIPs pays off. Piles for a light timber structure are short and few, an extension's worth goes in within a day, there is no spoil and no wait for concrete to cure. They work in gardens a digger cannot reach and between tree roots you want to keep. They cost more than a simple strip, they must be designed and load-tested to the engineer's figures, and the floor above is suspended, with a ventilated void beneath it.

The sole plate, and why level matters

Whatever is in the ground, the panels start from a treated timber sole plate, fixed down over a damp-proof course. Structural timber guidance keeps the underside of that timber at least 150 mm above finished ground level, so the slab edge or a course of brick or block is brought up as a kerb. Agree the height early: it sets your door thresholds.

Panels are factory-cut to the millimetre and cannot be trimmed to suit a wavy slab. Suppliers typically want the base level to within about 5 mm over its length and square across the diagonals. Ask for the figure in writing and have the groundworker work to the supplier's setting-out drawing, not the architect's plan.

Under the floor, a damp-proof membrane linked to the wall DPC keeps ground moisture out, as Approved Document C requires, and enough insulation goes in to bring the floor to 0.18 W/m²K.

Neighbours and sewers

Digging within 3 m of a neighbour's building, to a level below the bottom of its foundations, triggers the Party Wall etc. Act 1996. You serve notice at least a month before starting. The Act covers England and Wales.

If a public sewer runs within 3 m of the footprint you will need a build-over agreement from the water company. Find the drain runs before the design is fixed; moving an extension 500 mm on paper is free.

Foundations are priced from a trial hole and a drawing. Start with a quote for the extension and the groundwork together.

Get a quote

How the groundwork runs

  1. Trial hole

    Half a day

    A pit beside the house shows the soil and how deep the existing foundations go.

  2. Design

    1 to 3 weeks

    The engineer picks the type and depth; the SIPs supplier issues the setting-out drawing.

  3. Dig and pour

    1 to 2 weeks

    Building control inspects the open trench or the pile records before concrete goes in.

  4. Kerb and sole plate

    1 to 2 days

    Upstand, damp-proof course and levelled sole plate, ready for delivery day.

Typical durations. Yours depend on the design, the ground and the season.

Questions we get asked

What foundations does a single storey SIPs extension need?

On firm ground, ordinary concrete strip or trench-fill foundations. On soft or variable ground, a raft. Where there are trees, poor access or deep clay, piles or screw piles with a ring beam. An engineer or building control decides from a trial hole.

How deep should the foundations be?

At least 450 mm under Approved Document A, and usually at least 750 mm in clay. One metre is common, matching the existing house. Trees on shrinkable clay can push that past two metres.

Can a SIPs extension sit on a concrete slab alone?

Only if the slab is an engineered raft. A plain patio-style slab has no edge thickening or reinforcement and will not be accepted by building control.

Are screw piles accepted by building control?

Yes, when an engineer has designed them and the installer provides the installation records. Tell your building control body at the start so they can agree what evidence they want.

Do the foundations cost less than for a brick extension?

A little, where narrower trenches are allowed. The saving is modest because digging, inspection and concrete depth are much the same. The larger saving with SIPs is time on site.

Who builds them, the SIPs firm or a groundworker?

Usually a groundworker, working to the panel supplier's setting-out drawing. Firms that offer a full build will take on the groundwork as part of one contract.

Read next

Get a quote for your SIPs extension

Postcode, four quick questions about the build, then how to reach you. It takes about a minute and costs nothing.

We match homeowners with panel firms, free of charge, and do not build extensions ourselves. We look for a company that designs and erects SIPs extensions near your postcode and tell you its name. Your details go no further until you say yes.

Step 1 of 3

Where is the house?
Get a quote